Figure 3 - Install Pilot Assembly
WARNING
Fire, burn hazard. Do not operate boiler without
burner doors in place. Failure to follow these
instructions could result in death or serious injury.
!
NOTE: Refer to Figure 6 fi nal pilot tubing confi guration.
11.
Remove pilot assembly from box. Spin assembly so it
enters base between lower front panel and top of base.
See Figure 3.
12.
Push assembly into base. If needed, slide pilot tube
and spark wire (or thermocouple) through hole in lower
front panel. See Figure 4.
13.
Rotate pilot assembly until it is vertical and holes in
pilot assembly line up with pilot mounting holes in
top of base. Verify base insulation is over top of pilot
bracket, not in between bracket and base top. See
Figure 5.
14.
Fasten assembly using screws provided. After
fastening assembly, reach in base above bracket and
verify insulation is laying fl at against base front.
15.
Verify pilot assembly is correctly angled; at right angle
with top of base.
16.
Install burner tubes in base by sliding crimped end into
slots in back of base. Rest front of burner on orifi ces.
Replace upper burner door. See Figure 5.
17.
Final pilot tubing confi guration after completion all
steps see Figure 6.
18.
Refer to Installation, Operation and Maintenance
Manual and labels affi xed to boiler for lighting
instructions.
Figure 4 - Installed Pilot Assembly (3 Section Shown)
Figure 5 - Install Burner Door and Tubes
(3 Section Shown)
Figure 6 - Series 2 Final Pilot Tubing Confi guration
(2 Section Shown)
KIT INSTALLATION INSTRUCTIONS
ECR International, Inc.
2201 Dwyer Avenue, Utica NY 13504-4729
web site: www.ecrinternational.com